Tentative schedule for Interstate 35W / Highway 62 Reconstruction

Project letting: Mid-late March 2007

Community Meetings: May 2007

Contract Award: Late May - June 2007

June 2007 - June 2008 (Stage I)

The Diamond Lake Road Bridge and 58th Street Pedestrian Bridge will be removed.*
The Diamond Lake Road drainage work will be started.
Temporary widening on northbound I-35W and retaining wall work will start in the Commons Area.
Retaining walls on the east side of Lake Mead will be constructed.
Work will begin on the retaining walls, noisewalls and the frontage roads on both the east and west sides of I-35W. Noisewalls will be replaced as soon as it is feasible. Many of the noisewalls will be affected by retaining wall construction. Where this occurs, the retaining wall construction will dictate the length of time an area is without a noisewall.
* CNA Consulting Group will be contacting residents near the Diamond Lake Road Bridge to do foundation evaluations in preparation for pile driving for bridge abutments.
Back to top Go down
View user profile http://armatage.dynamicforum.net
 
Crosstown Reconstruction 2007 Schedule
Back to top 
Page 1 of 1
 Similar topics
-
» Fiona Payne Statement 4th May 2007
» Statement of Jane Tanner 10.5.2007
» VIDEO - RECONSTRUCTION: Why McCanns and Tapas 7 won't participate.
» calpol was avalible in 2007!!!
» Sky news video history starting 04 May 2007

Permissions in this forum:You cannot reply to topics in this forum
 :: Armatage General Discussion-
Jump to: